Upgradation of Control Systems at NFGP Plant
Silvertech has successfully executed an EPIC contract to upgrade the control systems of Sour Gas Compressor 6112-KT-01, Turbo Expanders 6103-K01-A/B, SRU Blowers/Compressors 9101-K-01 A/B and Flame Detectors 6112-F01/2, 6102 F01, 6848A-01 A/B and 9101 F-01/02/03 in Qatar Petroleum’s North Field Gas Plant (NFGP).
Silvertech supplied an Allen Bradley ControlLogix SIL2 PLC based system, which also includes:
- Bently Nevada 3500 Machinery Protection and Monitoring Systems
- CCC 3++ Anti-Surge Control Systems
The existing flame detectors were replaced with radio active interference free Fireye Enhanced UV Insight scanner.
Silvertech’s EPC scope also included:
- Endorsement of FEED
- Initial Design Engineering
- EPC Project Management,Planning, QA/QC, HSE
- Supply, design, testing, installation and commissioning of ControlLogix PLC System
- Supply, design, testing, installation and commissioning of Bently Nevada 3500 Machinery Protection and Monitoring Systems
- Supply, design, testing, installation and commissioning of CCC 3++ Anti-Surge Control Systems
- Field Installation Engineering
- Associated cable tray and cable trench works
- Documentation
Similar projects

ICSS Replacement at UAD Facilities - Offshore
Silvertech has successfully executed an EPC contract…
Technology : ICSS
Sector : Oil & Gas

Cluster-7 Well Platforms Project
Silvertech has successfully executed a contract for…
Technology : F&G
Sector : Oil & Gas

Fire & Gas System Replacement at NGL Area
Silvertech has successfully executed an EPC contract…
Technology : F&G
Sector : Oil & Gas